Offering over fifty years of experience constructing many Arizona projects, The Ashton Company is very well positioned for the years beyond 2000. Their sophisticated computer systems will meet any client's requirements for managing the scheduling and costing aspects of a project.

Public sector clients consider The Ashton Company a leading contractor. Private sector clients have learned that their projects are built in a seamless, productive environment by individuals accustomed to finding innovative solutions to challenges that confound other contractors.

In the twenty-first century, unforeseen circumstances can lead to difficulties. An experienced team of professionals with an unblemished track record has never been more important. That team is The Ashton Company.

Significant Projects

Ina Road Water Pollution Control Facility - New Headworks Facilities

Description: Construction of new junction structures, coarse screen facility, influent pump station, fine screens/grit basins, intermediate pump station, odor control systems, associated electrical and instrumentation, yard piping and site work
Value: $19,500,000
Client: Pima County Wastewater Management

Tucson/Benson Highway
Description: PCCP rehabilitation, spall and joint repair and asphaltic rubber friction course overlay
Value: $2,950,000
Client: Arizona Department of Transportation

Arizona Portland Cement - Marana, AZ
Description: Installation of water piping, installation of all mechanical equipment and piping for Rimod #3 project and installation of conveyors and transfer chutes
Value: $1,600,000
Client: Arizona Portland Cement

CAP Water Treatment Plant

Description: Modifications of Snyder Hill Pump Station including roof repairs and basin bottom liners as well as new pumps
Value: $1,900,000
Client: City of Tucson/Tucson Water Department

Pantano Wash
Description: Installation of bank protection, fencing, railings, sidewalks and driveways
Value: $1,500,000
Client: City of Tucson

Cholla Power Plant Coal Handling Modifications

Description: Modification of existing coal handling conveyors at reclamation tunnel
Value: $1,100,000
Client: Sundt Corp / APS

Back to top of page


Significant Projects

1991 Roger Road Wastewater Treatment Plant, Phase II
Description: New clarifier, pump station, biofilters, maintenance building, storage facility and modified grit removal facilities
Value: $7,300,000
Client: Pima County Wastewater Management

1992 Davis Dam - Kingman Highway
Description: Roadway excavation, construction of drainage structures including six bridges and base and asphaltic concrete pavement
Value: $13,850,000
Client: Arizona Department of Transportation

1993 Tucson Airport Groundwater Remediation Project
Description: Piping, feed equipment, water mixing equipment and instrumentation, construction of fiber optic data highway, installation of radio communications system and all related electrical work
Value: $5,000,000
Client: Tucson Airport Remediation Project Steering Committee

1994 Tank Farm

Description: Consisted of concrete foundations for six one million gallon steel tanks used for water reclamation and containment walls, structural steel platform, mechanical piping and electrical work
Value: $6,500,000
Client: Hughes Missile Systems Company

1995 Sun Tran Compressed Natural Gas Fueling Station
Description: Installation of three natural gas compressors, electrical switch gear, high-flow refuelers, high pressure gas storage and compressor cooling system
Value: $2,250,000
Client: City of Tucson

1996 Wetlands/Stage I, Roger Road Reclaimed Wastewater Recharge
Description: Secondary effluent pump station, conveyance/recovery piping, back water pumping modifications, sitework and planting, gravity piping and hydraulic structures, public amenities, landscaping and irrigation
Value: $4,700,000
Client: City of Tucson

1998 Linda Vista Booster Station and Reservoir
Description: Five million gallon potable water storage, reinforced concrete reservoir, natural gas engineer driven pump, piping valves and flow metering
Value: $2,900,000
Client: Metropolitan Domestic Water Improvement District

Back to top of page


Significant Projects


After only a few years in business, the skills of the company were being acknowledged by clients with major projects to be undertaken.

1951 St. Mary's Road Bridge - Tucson
1952 Central Heating and Cooling System - University of Arizona
1952 Business and Administration Building - University of Arizona
1953 20 Megawatt Power Plant - Phelps Dodge
1953 Hydrant Fuelling Station - Davis-Monthan Air Force Base
1955 Radar Station for Early Warning System - Ajo, Arizona
1956 Inlet, Tunnel and Outlet Works - Painted Rock Dam
1958 Shops and Yards for Kennecott Copper Co. - Ray, Arizona

In the 1960's the company moved more into the highway business, although many other major projects were completed.

1960
Sentinel - Aztec Portion of I-8 Interstate
1961 Benson - Willcox Portion of I-10 Interstate
1962 I-10 and I-19 Interchange
1964 Martin Reservoir - Tucson International Airport
1964 West Stadium Addition - University of Arizona
1966 Anaconda Power Plant
1968 Arizona Portland Cement Roll Crusher
1969 Primary Crusher, Anamax Copper Co. - Green Valley, Arizona

As the company continued to grow in the 1970's, both existing and new clients awarded projects that reflected the outstanding reputation being earned.

1971 Wastewater Plant - Flagstaff
1972 Wastewater Plant - Havasu City
1974 East Stadium Addition - University of Arizona
1975 Arizona Portland Cement Roll Crusher
1976 Asarco Reduction Works - Mission Mine
1977 Kennecott Tailings Dam - Hayden, Arizona
1979 Power Line Substations - Tucson Electric Power

1983 Magee Road Bridge
Description: Soil cement bank protection, new road and bridge across Canada Del Oro Wash
Value: $1,900,000
Client: Pima County Department of Transportation and Flood Control

1984 Ina Road
(S.P.R.R. to Thornydale Road & Thornydale Road to Mona Lisa)
Description: Grading, drainage, concrete structures and new road and bridge over the Canada Del Oro Wash
Value: $6,950,000
Client: Pima County Department of Transportation and Flood Control

1985 Swan Road (Ft. Lowell Road to River Road)
Description: Bridge over the Rillito River, 1.2 miles of roadway on Swan including RCP, catch basins
Value: $3,700,000
Client: Pima County Department of Transportation and Flood Control

1986 Swan Road
(River Road to Sunrise Drive)
Description: Constructing new asphaltic concrete pavement with concrete curbed medians, concrete curb and gutters, storm drains, pipe culverts, concrete lined channels, retaining walls and associated roadway and drainage improvements
Value: $6,200,000
Client: Pima County Department of Transportation and Flood Control

Back to top of page


Electrical
1999 Cathodic Protection Systems, Tucson Phase II Project

Description: Furnishing and installing cathodic protection systems, supplemental cables, electrodes and circuit board sets; installing ground rods, electrical conduit and insulated conductors
Value: $2,000,000
Client: Central Arizona Water Conservation District

2000 Roden Crater, Phase 1A-1
Description: Construction of Light Observatory
Value: $7,300,000
Client: Skystone Foundation/Roden Crater Project

2000 Asarco Tankhouse Renovation
Description: Electrical and instrumentation for tankhouse
Value: $1,100,000
Client: Asarco - Ray Complex

Wastewater
1986 City of Peoria - Beardsley Road Wastewater Treatment Plant
Description: Wastewater Treatment Plant
Value: $1,600,000
Client: City of Peoria

1990 Nogales International Wastewater Treatment Plant Expansion
Description: Expansion of the International Wastewater Treatment Plant between the U.S. and Mexico - all development, excavation, embankment, structural works; furnished, installed, and placed all equipment, mechanical and electrical
Value: $13,500,000
Client: International Boundary & Water Commission

1992 Pima County Wastewater Facilities, Roger Road Plant Upgrade Phase II
Description: Mass excavation, concrete, structural steel, process piping and mechanical equipment installation, new digester and heat exchangers
Value: $8,000,000
Client: Pima County Wastewater Management

1995 Pima County Wastewater Facilities, Roger Road Plant Upgrade Phase III & Dechlorination Facilities
Description: Work consisted of mass excavation, concrete, structural steel, process piping and mechanical equipment installation (new clarifiers, dechlorination facilities, digester gas reuse system)
Value: $17,500,000
Client: Pima County Wastewater Management

Mining

1996 BHP Copper Company- Various Projects
Description: 42" Boring at railroad, refinery fuel station rebuild, matte concrete storage slab, fabricated and installed spin filters, modified matte chip conveyors, two major outages, belt line modifications, modified slime and bucket elevators and miscellaneous maintenance work
Value: $4,000,000
Client: BHP Copper Company

1998 Asarco Incorporated Mission Complex

Description: Miscellaneous maintenance projects, maintenance overland conveyor, crusher MCC room (civil, mechanical and electrical), truck shop expansion and excavation and placement of one million cubic yards for Tailings Dam #4
Value: $5,900,000
Client: Asarco Incorporated

1988-1999 Camp Grant Yearly Mining Contract Silica and Limestone Crushing
Value: $11,000,000
Client: Magma Copper Company/BHP

1994 Rocky Gulch Excavation & Roadwork

Description: Repaired and widened existing road; constructed new roads, excavated sump, drilling and blasting required, excavated dam keyway, stockpiled rip rap rock
Value: $1,100,000
Client: Phelps Dodge Morenci, Inc.

1994 SX-EW Phase IV
Description: Site work, concrete and underground utilities, mechanical piping and electrical instrumentation for dust leach project
Value: $2,100,000
Client: Magma Copper Company/BHP

Back to top of page